Timeline to Summer Launch (5-6 months available) ​

Current date: January 23, 2026
Summer window: June 1 - August 31, 2026

Phased Approach ​

Phase 1: Feb (Weeks 1-4) - Legal + Core Backend

  • Complete trademark search & ToS/Privacy Policy (Issues #140-143)
  • Wire critical backend: Frens, Waves, Lantern lighting, User profiles
  • Merchant backend integration (signup β†’ approval β†’ offers)

Phase 2: March (Weeks 5-8) - Closed Beta

  • 5 merchants onboarded (using partner network)
  • 50-100 invited users (San Diego only)
  • Basic safety features: blocking, reporting
  • Heavy monitoring & iteration

Phase 3: April (Weeks 9-12) - Pilot Expansion

  • Scale to 15-25 merchants
  • 500-1000 users
  • Analytics/attribution infrastructure (Issues #64-65)
  • Cross-device testing & bug fixes
  • First revenue validation

Phase 4: May (Weeks 13-16) - Pre-Launch Polish

  • Advanced safety features (if needed)
  • Marketing materials & go-to-market strategy
  • 50+ merchants recruited
  • Performance optimization
  • iOS/Android PWA testing

Phase 5: June 1 - Soft Launch πŸš€

  • Staged rollout: San Diego first
  • Monitor for 2-4 weeks
  • Expand to adjacent markets (Orange County, LA)

Phase 6: July-August - Full Summer Launch β˜€οΈ

  • Public marketing campaigns
  • Scale to 100+ merchants
  • Multi-market expansion
  • Influencer partnerships

Why This Works ​

  1. Strong foundation already built: Auth, venues, UI, deployment, security
  2. Clear scope: 37 open issues, most are enhancements not blockers
  3. Defined business model: Merchant pilot strategy already documented
  4. High dev velocity: 50+ commits in January alone
  5. Lean MVP mindset: Can launch without every feature (SOS, dark mode, etc.)

Critical Path Items ​

Must-Have for Launch:

  • βœ… Legal compliance (ToS, Privacy Policy, trademark) - 2 weeks
  • βœ… Core mechanics working (light lantern, wave, frens) - 3 weeks
  • βœ… Merchant system end-to-end - 2 weeks
  • βœ… Basic safety (block, report) - 1 week
  • βœ… 25-50 merchants recruited - ongoing from March

Nice-to-Have (can defer):

  • SOS emergency system (Issue #128) - Phase 2 post-launch
  • Advanced analytics dashboard (Issues #64-65) - MVP version sufficient
  • Dark mode (Issue #116) - post-launch
  • Separate merchant portal (TODO.md) - not needed until 50+ merchants

Realistic Summer Launch Scenarios ​

Conservative (June 15):

  • 4 weeks cushion for unexpected delays
  • Start with invitation-only in 2-3 cities
  • 30-50 merchants

Aggressive (June 1):

  • Everything on track
  • San Diego + Orange County
  • 50+ merchants

Aspirational (July 4 weekend):

  • Peak summer marketing moment
  • 3-5 cities
  • 100+ merchants
  • Press coverage

The Bottom Line ​

You have 21 weeks until June 1 and 27 weeks until August 31.

Based on your current progress, development velocity, and the well-documented business strategy, a summer launch is not just realisticβ€”it's highly achievable if you:

  1. Prioritize ruthlessly: Legal + core features only for closed beta
  2. Iterate in market: Launch lean, improve based on real feedback
  3. Merchant-first: Get 5 merchants by March, expand from there
  4. Accept imperfection: Ship with 80% of features, not 100%