Alpha โ€‹

Summer 2027. Code name Aurora. Invite-only. San Diego, a small invited group plus one or two pilot venues, run as target launch events.

Alpha proves two things: that two anonymous people approach each other, and that people felt safe doing it.

Alpha starts from the December 2026 Prototype release: the product already built and deliberately attacked and verified. What remains is legal clearance, taking it to production, and putting it in front of invited outsiders.

Phases are sequential. See Phases.

Phase 1: Clear โ€‹

Legal clearance obtained. None of it blocks the December Prototype release (operator, 2026-08-31); it becomes binding here, where outsiders arrive. Long-lead items (trademark, counsel review) can and should start during Prototype.

TaskCategoryPriorityDescriptionWhyStatusIssues
ToS and Privacy PolicyLegal๐Ÿ”ดย P0Final, counsel-reviewed, published, and reachable from the appPublic signup without them is not an option. The pages exist and the app footer now reaches them; the counsel-review and publishing half is undecidedโ“ Needs operator input#141, #837
Trademark clearanceLegal, Business๐Ÿ”ดย P0Clear the mark for our use and markets. No conflicting USPTO registrations, classes 35 / 42 / 43, roughly $1,450 USAn explicit pre-launch gate๐Ÿšง In progress#140
Business legalities and governanceLegal, Business๐Ÿ”ดย P0Entity, Employee Rights Charter, governance docs signed offFounding paperwork gets harder with users attachedโ“ Needs operator input#896

Phase 2: Ready โ€‹

Distribution decided, production cut over.

TaskCategoryPriorityDescriptionWhyStatusIssues
App-store-wrapper decisionEng, Business๐Ÿ”ดย P0Ship as PWA only, or wrap for the storesAn explicit pre-launch gate, and it changes the timelineโฌœ Not started#163
Cutover to productionEng๐Ÿ”ดย P0Finalize and push to prod, including a full pre-launch token and secret rotationEverything above is only real once it shipsโฌœ Not started#76
Devops hardeningEng, Ops๐ŸŸ ย P1Senior sign-off before merge, required checks on dev, a rollback path, deploy monitoringA written norm that nothing enforces is not a controlโฌœ Not started#164
Pre-launch penetration re-testEng, Safety๐Ÿ”ดย P0Re-run penetration testing against the production buildThe December pen test proves the December build; six months of change and a new environment need their own pass (operator agreed, 2026-08-31)โฌœ Not started#865

Phase 3: Recruit โ€‹

Venues, merchants and invitees committed. Gated on Clear and Ready.

TaskCategoryPriorityDescriptionWhyStatusIssues
Pilot venue agreementsBusiness, Growth๐Ÿ”ดย P0Venues that agreed to be pilots, with a named contact and an understanding of what participating involvesManufactured density needs venues that said yesโ“ Needs operator input#868
Repeatable pitchBusiness, Growth๐Ÿ”ดย P0The merchant story, partnership terms, objection handlingRecruiting past the first friendly venue needs a scriptโ“ Needs operator input#869
Sales and onboarding processBusiness, Growth๐Ÿ”ดย P0Who reaches out, what they send, how a signed merchant gets liveNeeds a dedicated process, not ad hoc effortโ“ Needs operator input#870
Marketing materials and GTMBusiness, Growth๐Ÿ”ดย P0Positioning, launch assets, channel planInvited people still need to be told what this is and whyโ“ Needs operator input#326, #199
Partnership model for first merchantsBusiness, Growth๐ŸŸ ย P1Early merchants do not pay: free advertising for life in exchange for data and calibrationPricing an unproven system is guessworkโฌœ Not started
Partner network activationBusiness, Growth๐ŸŸ ย P1Working existing contacts into the cohortCheapest source of merchantsโ“ Needs operator input
"Scheduled lanterns" positioningDesign, Business๐ŸŸ ย P1Going somewhere with a buddy, closer to a yoga class than an eventWrong framing recruits the wrong first usersโฌœ Not started#964
Offer review processBusiness, Safety๐ŸŸ ย P1Named reviewers plus written guidelines for approve or rejectA review queue with no standard behind it decides ad hocโฌœ Not started

Phase 4: Run โ€‹

The launch events themselves.

TaskCategoryPriorityDescriptionWhyStatusIssues
Target launch eventsBusiness, Safety๐Ÿ”ดย P0What the events are, their shape, and whether they run once or ongoingThe events ARE the experiment designโ“ Needs operator input#871
Safety-comfort measurementSafety, Business๐Ÿ”ดย P0How we ask whether people felt safe, keeping groups visible instead of averagingOne of the two things Alpha exists to answer, and the instrument has to exist before the events doโ“ Needs operator input#867
First revenue validationBusiness๐ŸŸ ย P1A merchant pays, and the value is defensibleProves the model once the free-partnership cohort has runโฌœ Not started

Runs throughout โ€‹

TaskCategoryDescriptionStatusIssues
Hire a second engineerBusinessRecruit and onboard a second senior engineerโ“ Needs operator input#873
Google Workspace and SlackBusiness, OpsShared email, calendar and chat, with the per-seat cost modelled into the billing pipeline firstโ“ Needs operator input#872
Every P0 tracked as an issueOpsEvery P0 on this page has an issue behind it๐Ÿšง In progress
Business plan finalizedBusinessThe canonical plan closed out๐Ÿšง In progress